Casa Daily Cost Guides

Townhouse development cost in Brisbane

$3,800,000–$4,700,000complete 4-pack townhouse project including land

Indicative all-in cost for a Brisbane LMR2 4-pack townhouse project: land $1.0M–$1.4M, build $2.4M–$2.8M (4 × 3-bed at $600–700K each), planner/architect/engineer $80K–$120K, infrastructure charges $60K–$80K, finance and holding $200K–$300K. Total project cost $3.8M–$4.7M. End values $4.6M–$5.6M (4 × $1.15M–$1.4M each). Gross developer margin 16–22%.

Line-by-line cost breakdown

Line itemRangeNotes
Land acquisition (LMR2, ~1,000m²)$1,000,000–$1,400,000Coorparoo, Annerley, Holland Park premium; Salisbury, Stafford lower.
Build cost (4 × 3-bed townhouses)$2,400,000–$2,800,000$600–700K per dwelling, including site costs.
Planner + architect + engineer$80,000–$120,000MCU + Operational Works + design package.
Council application fees$8,000–$18,000MCU + OPW + Building Works.
Infrastructure charges$60,000–$80,000BCC ~$15–22K per additional dwelling × 3 (1 credit).
Stamp duty$38,000–$55,000Approx 4% on land purchase.
Finance and holding$200,000–$300,000Across 24–36 month timeline.
Marketing + sales$80,000–$180,000Agent commission + marketing per dwelling.
Total$3,800,000–$4,700,000complete 4-pack townhouse project including land

Variables that move the total

  • Pack size

    3-pack drops total ~25%; 6-pack scales up but often triggers Impact Assessable.

  • Sub-precinct

    LMR2 vs LMR3 — LMR3 permits 3-storey townhouses and apartment buildings.

  • Finish level

    Mid-range $600K per dwelling; premium $700K+ with stone, timber details, larger living areas.

  • Slope

    Cross-fall >1:8 adds $40–120K total for retaining and slab works.

  • Flood / overlay

    Binding flood overlay can add $80–200K total for freeboard across all dwellings.

What's NOT included in the total

  • GST on land (input-taxed for residential).
  • Owner-occupier inclusions if retaining one dwelling.
  • Capital gains / income tax.

Common questions about townhouse development cost in brisbane

What's the minimum lot size for 4 townhouses in Brisbane?
Brisbane City Plan permits Multiple Dwelling Code Assessable in LMR2 with a typical minimum lot area of 800m² for a 4-pack, depending on density permitted. The Casa Daily Subdivision Checker reads the precinct mapping for your specific lot.
What's the timeline for a Brisbane townhouse project?
Code Assessable: 9–15 months DA → 12–18 months construction → 6–12 months settlements. Total 27–45 months from land settlement to final townhouse settlement.
What gross margin should I target?
20–25% on Code Assessable LMR2 4-packs in middle-ring Brisbane. Below 18% is too tight for the risk; above 28% means you've underestimated build, finance, or selling cost — re-check.

Related